About our new home construction service
Building a new home is the biggest project most families take on. We manage the whole build: design, permits, excavation, foundation, framing, roofing, mechanical systems and every interior finish. You deal with one team and one schedule.
Whether you are replacing an older house on a lot you love, building a duplex or multiplex for income, or adding a garden or laneway suite, we start with drawings and permits and build to Ontario's Building Code. In Ontario, new homes must be built by a builder licensed by the Home Construction Regulatory Authority and come with a Tarion warranty. Ask us about our licence and warranty when we meet.
What's included
What we build
- Custom home building (design-build)
- Building from the client's own plans
- Knockdown and rebuild (demolish the old house, build new)
- Infill, laneway and garden suite homes
- Semi-detached, duplex and multiplex builds
- Energy-efficient and net-zero homes
Every stage of the build
- Lot clearing, excavation and grading
- Foundations (poured concrete, ICF, block)
- Framing (wood, steel)
- Roofing
- Full interior finishing (drywall, flooring, trim, paint)
- Turnkey builds, including landscaping and driveway
Rendering of completed home
How your project runs
Site visit
We look at the space, talk through your goals and check zoning and permit needs.
Drawings and estimate
You get a written, itemized estimate and a schedule. We prepare drawings and permits.
Build
One project manager runs the trades and keeps you updated each week.
Inspect and hand over
We book every inspection and walk you through the finished work.
What a custom home build includes, from survey to keys
A custom home build covers far more than the house itself. Before any concrete is poured, someone has to survey the lot, confirm what zoning allows, design to the Building Code, protect trees, arrange service connections and get every permit. We plan all of it as one project with one schedule.
Here is what a typical knockdown rebuild or new custom home in Hamilton, Brampton, Kitchener or Cambridge includes from start to finish:
- Site work: topographic survey, utility locates through Ontario One Call, gas and hydro disconnects, demolition, tree protection hoarding and excavation.
- Structure: footings set below frost depth (at least 1.2 m below finished grade in most southern Ontario soils), foundation walls with damp-proofing and drainage, framing, engineered floor systems and roof trusses.
- Envelope: roofing, windows, air barrier, insulation and cladding such as brick, stone, stucco or cedar. Our three-storey infill home in the projects gallery pairs stucco with cedar cladding and a two-car garage.
- Systems: water and sewer connections, plumbing, a new electrical service, HVAC sized from heat-loss calculations, and ventilation. Our plumbing, electrical and HVAC work is coordinated from the drawings stage.
- Finishes and exterior: drywall, flooring, trim, kitchens, bathrooms, then grading, driveway and landscaping on turnkey builds.
The scope you choose decides the price. Some clients want a fully finished turnkey home. Others want us to build to drywall and handle finishes themselves. We write the scope down line by line so you know exactly what is included.
How much it costs to build a custom home in Hamilton and the surrounding area in 2026
Most custom homes in Hamilton, Brampton and Kitchener-Waterloo cost between $325 and $575 per square foot of finished space to build in 2026, and high-end builds often go past $575. Land is extra. The number per square foot hides a lot, so treat these figures as a starting point and expect an exact price only after we see the lot and your drawings.
| Build level | Typical construction cost (CAD per sq ft) | What it usually means |
|---|---|---|
| Standard custom | $325 to $425 | Simple footprint, builder-grade windows, vinyl or engineered flooring, standard cabinetry |
| Mid-range custom | $425 to $575 | More complex roof and massing, upgraded windows, hardwood, custom kitchen, finished basement |
| High-end custom | $575 to $800+ | Large glazing, steel, stone, premium mechanical systems, high-end millwork and fixtures |
Several costs sit outside the per-square-foot figure. Plan for each of them separately:
- Demolition: taking down an older house and removing its foundation often runs $25,000 to $60,000 or more. Asbestos found in old insulation, flooring or plaster adds to it.
- Design and approvals: drawings, structural engineering, surveys, arborist reports, permit fees and any minor variance.
- Servicing: new water and sewer connections to the street, a new hydro service and gas meter.
- Development charges: covered in the next sections. They depend on your city and the number of units.
- Exterior work: driveway, interlock, fencing and landscaping if they are not in your contract.
Keep a contingency of 10% to 15% of the construction budget. On a new build the biggest surprises are below ground: poor soil, high groundwater or old buried foundations.
Knockdown rebuild or major renovation: how to decide
A knockdown rebuild usually makes sense when the old house needs structural, foundation and mechanical work all at once. Once a renovation touches every system, you pay to work around old framing and low ceilings and still end up with an old foundation. A rebuild lets you fix the layout, ceiling heights and energy performance from the ground up.
We compare the two options on the same lot using these questions:
- Is the foundation sound? Cracked or bowing walls, a low basement and chronic leaks push toward a rebuild. A solid foundation with a shallow basement can often be saved with underpinning.
- How much space do you need? If an addition or second storey gets you the space and the house is sound, renovating is usually cheaper.
- What does zoning allow? Older houses sometimes sit closer to the lot line than today's by-law allows. A renovation may keep that legal non-conforming position. A new house has to meet current setbacks or get a variance.
- How long can you be out of the house? A rebuild means moving out for roughly a year or more. A large renovation often means moving out too.
When the renovation estimate passes about 60% to 70% of the rebuild price, most owners choose to rebuild. You get a new structure, new systems and a Tarion warranty on the new home. If the numbers are close, we lay out both prices side by side.
What you can build: zoning, multiplexes and garden suites
Your zoning by-law decides the size, height and number of units you can build. It sets setbacks from each lot line, maximum height, lot coverage and in some zones a floor space limit. We check all of these before design starts, because a house that fits the by-law goes straight to a building permit.
Ontario law lets you build up to three residential units on most serviced residential lots: for example a main house with a basement apartment plus a garden suite. Each of the cities we serve sets its own limits on top of that:
- Hamilton (including Stoney Creek): up to four units are allowed in some zones. A detached unit in the rear or side yard needs a direct exterior exit and a fire access path at least 1.0 m wide with 2.1 m of clearance from the street, and it must be serviced through the main house. A new detached unit is covered by the Tarion new home warranty.
- Brampton: the zoning by-law allows a maximum of three units including the main house, as either two units in the house plus a garden suite, or three units in the house. A garden suite starts with the Planning Division before the building permit.
- Kitchener: up to four units are permitted on many residential lots, with up to two of them in a detached backyard home. Some lots allow fewer because of servicing or natural hazards.
- Cambridge: up to three units in total, as three in the main building or two in the main building plus one in a detached structure.
A multiplex is a bigger build than a single house. It needs fire separations between units, separate exits, and often sprinklers or extra fire protection depending on the layout. A building of three storeys or fewer with up to four units usually stays under Part 9 of the Ontario Building Code, which keeps design simpler. Larger buildings can fall under Part 3, with more engineering and longer reviews.
Development charges for new homes and extra units
Development charges are one-time fees cities, regions and school boards collect on new housing to pay for roads, water and transit. On a brand-new house on a vacant lot they can be very large, and the amounts differ a lot between the cities we serve:
- Hamilton: for a single or semi-detached house in the urban area, City and education charges total about $84,900 to $106,000 for permits from June 1, 2026 to May 31, 2027, depending on the sewer area. See the city's 2026 to 2027 development charges pamphlet.
- Brampton: City, Region of Peel and school board charges for a single or semi-detached house totalled about $154,400 as of July 1, 2026. The rates are indexed every February 1 and August 1, as Brampton's development charges page explains.
- Kitchener: the City's own charge for a single detached house is $21,215 to $31,587 depending on the area, and the Region of Waterloo and the school boards add their own charges. Kitchener's development charges page lists the city rates.
- Cambridge: City and Region of Waterloo charges apply to new houses. We confirm the current figure with the city when we price the job.
Several exemptions help homeowners building new. Under the Development Charges Act, a second and third unit in a new detached, semi-detached or row house are exempt, as is one unit in an ancillary building such as a garden suite, within set limits. Hamilton's pamphlet lists a full City exemption for up to two additional units, and Cambridge states that neither the city nor the Region collects charges on ARUs. Kitchener offers a grant toward the school board charges on units 2 and 3, and toward part of the charges on a fourth unit. School board charges can still apply in some cases.
A knockdown rebuild usually pays far less. Hamilton credits the house you demolish for up to 5 years after the demolition permit is issued. Timing matters too: Hamilton collects City charges on non-rental houses at occupancy, while Brampton and Kitchener collect them before the building permit is issued. Ask us to confirm the figure for your lot when we price the job.
The custom home building process, step by step
A new home goes through the same stages in every city we serve. What changes is how long each one takes. We give you a written schedule with these stages before we start, and our full custom home building guide explains each one in more depth.
- Feasibility (2 to 4 weeks): we review the survey, zoning, trees, services and any heritage or conservation authority rules, then give you a budget range.
- Design (6 to 12 weeks): floor plans, elevations and material choices, followed by structural engineering, heat-loss calculations and energy compliance.
- Approvals (1 to 6 months): building permit, demolition permit, tree permits and, if needed, a minor variance. Our design and permits team handles each application.
- Demolition and excavation (2 to 4 weeks): disconnects, abatement if needed, demolition, shoring where the dig is close to a neighbour, and excavation.
- Foundation (3 to 5 weeks): footings, walls, waterproofing, weeping tile and backfill, each inspected.
- Framing and roof (6 to 10 weeks): framing, sheathing, windows and roofing until the house is closed in.
- Rough-ins (4 to 6 weeks): plumbing, electrical, HVAC and ventilation, then city framing and rough-in inspections and an ESA inspection.
- Insulation and drywall (4 to 6 weeks): insulation inspection, then drywall, taping and priming.
- Finishes (8 to 14 weeks): flooring, cabinets, tile, trim, paint and fixtures.
- Exterior and closeout (2 to 6 weeks): grading, driveway, final inspections, occupancy, and a pre-delivery inspection walk-through with you.
Some stages overlap, which is why construction typically lands in the 9 to 14 month range for a detached custom home.
Rendering of completed home
HCRA licensing and the Tarion warranty: what protects you
In Ontario it is illegal to build or sell a new home without a licence from the Home Construction Regulatory Authority (HCRA). When you hire a builder to build a custom home on land you own, that builder must be licensed as both a builder and a vendor. You can look up any builder in the HCRA Ontario Builder Directory before you sign.
The home also needs to be enrolled with Tarion. Tarion's statutory warranty on a new home has three layers:
| Coverage | What it covers |
|---|---|
| One year | Defects in workmanship and materials, Building Code violations, and the home being fit to live in |
| Two years | Water getting in through the foundation, windows or building envelope; defects in electrical, plumbing and heating distribution; detaching or deteriorating cladding |
| Seven years | Major structural defects that cause structural failure or seriously affect use of the home |
For a contract home on your own land, Tarion also protects money you pay the builder under the contract, up to $40,000, if the builder fails to substantially perform. Read the details on Tarion's warranty page.
Tip: Building the house yourself as an owner-builder may not need a licence if you live in it and don't sell it, but the home then has no Tarion warranty, and you take on permits, site safety and trade contracts yourself.
Common new-build problems and how we prevent them
Most new-build problems in Hamilton, Brampton, Kitchener and Cambridge start on the site. Infill lots are narrow, neighbours are close and the soil is often clay. These are the issues we plan for from day one:
- Drainage and grading: a new house with a deeper basement changes how water moves across the lot. We follow the approved grading plan, slope the ground away from the walls and direct downspouts so water stays off your foundation and your neighbour's.
- Damage to neighbours: excavation next to an older house can undermine its footings. We photograph neighbouring walls before work starts and use shoring or staged digging where the engineer calls for it.
- Trees: tree rules differ by city. Brampton requires a permit to remove a private tree 30 cm or more in diameter that stands more than 2 m from an occupied building. Kitchener requires a tree conservation permit on properties over 0.405 ha (1 acre). Hamilton has no single private tree by-law, though older Ancaster and Dundas by-laws still apply and tree services must hold a city licence. Tree hoarding goes up before demolition, and footings near roots can be redesigned.
- Groundwater: where the water table is high, we plan for sump systems, extra drainage or waterproof membranes on the foundation.
- Schedule slip: long-lead items like windows, steel and custom cabinets are ordered from the approved drawings so they arrive when the site is ready.
- Change orders: late design changes are the biggest cause of cost overruns. Finalize finishes before framing ends, and every change gets a written price before we build it.
Questions to ask a custom home builder in Ontario
A custom home is a contract worth hundreds of thousands of dollars, so check the builder as carefully as the design. Ask every builder you interview the same questions and compare the written answers.
- What is your HCRA licence number, and will my home be enrolled with Tarion before construction starts?
- Is your quote fixed-price or cost-plus, and what allowances are included for finishes?
- Which items are excluded: demolition, servicing, development charges, landscaping, appliances?
- Who prepares the drawings and engineering, and who deals with the city if the examiner has comments?
- Do you have WSIB coverage and liability insurance, and can I see the certificates? You can check WSIB status yourself through its clearance certificate service.
- How is the payment schedule tied to completed stages, and how is the 10% holdback handled under Ontario's Construction Act?
- Who is on site day to day, and how often will I get schedule and budget updates?
- Can I see a home you built that is similar in size and style?
Be wary of a price far below the others. It usually means a missing scope item that will come back as an extra. When you are ready, send us your lot address and ideas through the free quote form and we will start with a feasibility review.
New home construction: common questions
How long does it take to build a custom home?
Design and permits usually take 3 to 6 months, depending on your city and whether a minor variance is needed. Construction typically takes 9 to 14 months for a detached custom home. We give you a written schedule before we start.
Can you build from plans I already have?
Yes. We review your drawings, confirm they are ready for permit, and price the build from them. If anything needs engineering or changes, we flag it early.
Is a knockdown rebuild better than a major renovation?
If the house needs new foundations, structure and mechanical systems, rebuilding is often simpler and gives you a better result. We can price both options so you can compare.
Will my new home have a warranty?
New homes in Ontario are covered by the Tarion new home warranty, which protects you against defects for set periods after you move in. We explain the coverage before you sign.
How much does a knockdown rebuild cost in Hamilton?
The total is the construction cost per square foot plus demolition, design, permits, servicing and any development charges. See the cost table above for typical ranges; an exact price comes after we review your lot and drawings.
Can I build a fourplex on my lot?
In Kitchener, up to four units are permitted on many residential lots, and Hamilton allows four units in some zones. Brampton and Cambridge cap most lots at three units. We check your lot before design starts.
Do I pay development charges on a replacement house?
Usually much less than a new house on a vacant lot, because development charge by-laws generally credit the house you demolish. Hamilton gives that credit for up to 5 years after the demolition permit. New extra units may also be exempt. We confirm the rules for your city when we price the build.
Can I build a garden suite behind my house?
Ontario law allows one unit in an ancillary building on most serviced lots, and Hamilton, Brampton, Kitchener and Cambridge all permit garden suites or detached units on many residential lots. Size, height, fire access and distance from the main house are set by your zoning by-law.
Do I need to move out during a knockdown rebuild?
Yes. The house is demolished, so you will need somewhere to live for the full build, typically a year or more including demolition and finishes.
Can I live in the house before every finish is done?
Ontario allows occupancy of a new house once the city confirms that key items such as structure, fire safety, plumbing, heating and exits are complete. Minor finishes can be completed afterwards.
How do I check that a builder is licensed?
Search the builder's name in the HCRA Ontario Builder Directory on the HCRA website. It shows licence status and any conduct history.
Helpful resources
Official guidance we follow on every new home construction project:
- Check a new home builder’s licence — Home Construction Regulatory Authority
- Know your new home warranty — Tarion
- Ontario's Building Code — Government of Ontario
- Building permit requirements in Hamilton — City of Hamilton
- When you need a building permit in Kitchener — City of Kitchener
- Building permits in Cambridge — City of Cambridge